Pool Progress

( Click on the picture to get a full page view.)




Preparing for Monday's Grand Opening Barbecue.





Pool and Spa are completely full. Chemical treatment begins first thing in the morning, June 11.




Water is filling our pool again.





Plastering today. Nearly finished and looking good. Water likely being added later today.





New, double handrails on the spa Tile trim  with new depth markers around the sides.





Putting oncrete on the steps and benches in the spa.





Tile work on the steps and around the top is happening today.





Demo completed. Next phase set to begin on Friday, May 29th.




Demolitiion on the pool begins.
Demolition on the spa begins.




The pool is beginning to empty.
One very empty pool.